Company history
What you need to know about
Zarafshon Oyna
- «Zarafshon Oyna», established in November 2017.
- The initiator's own participation in the project is $175 million
- The total cost of the project is $250 million
- The loan from Asaka Bank is $75 million.




Presented to the President
During his visit to Navoi region
On March 2, 2018, the project of a new country led by Evgenia in New Russia and its leadership was presented.
In 2019, construction of the plant began and a loan was allocated from Asaka Bank for the purchase of technological equipment from Germany.
By Presidential Decree
On January 9, 2020, by Decree of the President of the Republic of Uzbekistan No.PP-4563, the project was included in the Investment Program of the Republic of Uzbekistan for 2020-2022.




Navoi Economic Zone
The initiator of the project, on his own, built a glass factory production complex from scratch on a land plot with a total area of 38 hectares. The total building area was 117,000 square meters.
The first glass was obtained
On October 3, 2022, the first glass was received, and on October 7, the production of finished products began.




Commissioning of a quartz sand processing plant.
In 2024, a quartz sand mining and processing plant with a capacity of 55 tons/hour was put into operation.

Products
The production capacity of the plant is 16 million square meters of flat glass per year.

Quality control

Equipment
The company has installed technological equipment from HORN Glass Industries AG, Germany